Fourth

07/06/22 - The paving contractor working on W. Fourth Street has some repairs to make between Main Street and the West Alley on the south side along Chase Bank. The Police Department will be placing meter bags on the meters in said area north and south side of West Fourth from Main to the west alley early in the morning. Repair work time is unknown at this time. It is believed to be less than 8 hours.

 06/24/22 - Fourth St will remain open to local traffic only, please use caution while driving around the barricaded work.  

06/17/22 - DiPonio (the project contractor) will continue with structure adjustments, concrete prep, and cleanup on Fourth St. 

06/13/22 - DiPonio (the project contractor) will continue with structure adjustments, concrete prep, and cleanup on Fourth St. Although asphalt pavement has been installed on Fourth St, the road remains under construction, specifically due to the removals, adjustments, and installation of concrete collars around the drainage structures. Fourth St will remain open to local traffic only, please use caution while driving around the barricaded work. 

06/08/22 - The paving contractor, working under Diponio, will be starting the pavement Thursday morning at 6:30 AM. The project limits are from Main Street through Walnut, Pine, Oak up to Wilcox and multiple driveways along the way. There will be moments of traffic disruption at all of these locations. The alleys will be closed from University through to Third for a period of time due to road cuts to perform the paving. It is recommended that business owners schedule deliveries earlier in the morning Thursday or schedule for Friday. The basecoat of Fourth will be completed and it will be a easier to allow traffic to cross Fourth at this point.

06/03/22 - DiPonio (the project contractor) will complete roadway grading and concrete flatwork. Asphalt paving will occur during the week.  Inconveniences can be expected, there will be time frames where roadway/driveway access will become restricted due to the concrete installation and asphalt paving on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

 05/21/22 -  The contractor has started cutting in grades which causes elevation differentials grade changes from hard surface to soft surface in the intersections. There are ramps installed for Main St., West Alley, Walnut, Oak, and at Wilcox and other driveways associated to the project. These changes will not be for long it’s just part of the process.

05/20/22 - DiPonio (the project contractor) will continue with roadway excavation and aggregate base installation. New concrete curb installation will take place this week, with flatwork possibly beginning at the end of the week. Inconveniences can be expected, there will be time frames where driveway access will become restricted due to the concrete installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.


05/13/22 - DiPonio (the project contractor) will continue with concrete removals, roadway excavation, and aggregate base installation. New concrete installation may occur towards the end of the week. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

05/06/22 - DiPonio (the project contractor) will continue with storm sewer installation, concrete removals, roadway excavation, and aggregate base installation. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

04/29/22 - DiPonio (the project contractor) will continue with utility work, including storm sewer, water main connections, and water service replacement, which will include scheduled events where you may be without water. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

04/18/22 - DiPonio (the project contractor) will continue with utility work, including storm sewer, water main connections, and water service replacement, which will include scheduled events where you may be without water for short period of time. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

04/01/22 - DiPonio (the project contractor) will continue with the installation of water main throughout the week. Work will include connections and water service replacement, which will include scheduled events where you may be without water. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

03/28/22 - DiPonio (the project contractor) will continue with the installation of water main throughout the week. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day. 

03/21/22: - Diponio (the project contractor) will begin mobilizing equipment and material on Fourth St. beginning Monday 3/21. Pavement removal will take place in the middle of the week, Wednesday or Thursday, weather permitting. Installation of water main will begin at the end of the week. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.